Turbogenerator for Russian fast reactor delivered

The delivery of the turbogenerator – comprising a steam turbine rotor and a stator – was carried out via the Northern Sea Route and then along the Ob and Tom rivers, after transshipment at the river port by special road transport.

The stator weighs 245 tonnes and measures 8 metres long, about 4.5 metres high and 4.8 metres wide. The turbine rotor, also delivered by water, weighs 98 tonnes. The generator rotor was also delivered by rail.


(Image: TVEL)

“The turbogenerator of the BREST-OD-300 power unit is a unique Russian development with fully air cooling,” said Ivan Babich, director of the power unit project. “The design is distinguished by increased safety and productivity. For the Tomsk energy system, this will be the most powerful power plant.”

Russia’s state nuclear corporation Rosatom announced in November last year that installation work had begun for the condenser in the turbine hall for the BREST-OD-300. At that time, it said installation of the turbine and generator was planned to start in 2025.

The background

The BREST-OD-300 fast reactor is part of Rosatom’s Proryv, or Breakthrough, project to enable a closed nuclear fuel cycle. The 300 MWe unit will be the main facility of the Pilot Demonstration Energy Complex at the Siberian Chemical Combine site. The complex will demonstrate an on-site closed nuclear fuel cycle with a facility for the fabrication/re-fabrication of mixed uranium-plutonium nitride nuclear fuel, as well as a used fuel reprocessing facility.

A progress update in November said that the cooling tower had been built, the walls of the reactor containment building erected and the reactor shaft and the enclosing structure of the reactor vessel have also been installed.

Earlier this month, Rosatom announced that the Atommash plant in Volgodonsk – part of its Mechanical Engineering Division – had shipped to the BREST-OD-300 construction site the central void shell and inner casing for the core support barrel, components which will hold nuclear fuel once installed. The Izhora plant in St Petersburg – also part of the same Rosatom division – shipped four peripheral cavity shells which will house steam generators and pumps for circulation of the coolant.

Initial operation of the demonstration unit will be focused on performance and after 10 years or so it will be commercially oriented. The plan has been that if it is successful as a 300 MWe (700 MWt) unit, a 1200 MWe (2800 MWt) version will follow – the BR-1200.

   

  • Related Posts

    US uranium production up again

    US mines produced 1,388,000 pounds U3O8 (534 tU) in 2025, up from 677,000 pounds U3O8 in 2024. The 2025 figure was the highest since 2016’s production of 2,545,000 pounds, according…

    Sogin begins re-encapsulation of uranium-thorium fuel

    Between 1968 and 1970, 84 elements of irradiated fuel from the uranium-thorium cycle from the Elk River experimental reactor in Minnesota, USA, were shipped to the Rotondella plant for reprocessing…

    Have You Seen?

    Afrigen Energy Invites Investors and Strategic Partners for Financing of 50 MW Private Solar PV Project

    • June 27, 2026
    Afrigen Energy Invites Investors and Strategic Partners for Financing of 50 MW Private Solar PV Project

    Global Utilities and Manufacturers Unite to Strengthen Grid Supply Chains Amid Rising Electrification Demand

    • June 27, 2026
    Global Utilities and Manufacturers Unite to Strengthen Grid Supply Chains Amid Rising Electrification Demand

    Infinity Power Selects AIKO as Sole PV Module Supplier for Egypt’s 1.2 GW Nefer Menya Solar and 600 MWh Battery Storage Project

    • June 27, 2026
    Infinity Power Selects AIKO as Sole PV Module Supplier for Egypt’s 1.2 GW Nefer Menya Solar and 600 MWh Battery Storage Project

    Oil Prices Dive as More Tankers Move Through Strait of Hormuz

    • June 27, 2026
    Oil Prices Dive as More Tankers Move Through Strait of Hormuz

    AMERICAN ENERGY SNAPSHOT: America’s Strategic Petroleum Reserve

    • June 27, 2026
    AMERICAN ENERGY SNAPSHOT: America’s Strategic Petroleum Reserve

    Magnolia Oil & Gas Is in Lead to Acquire WildFire for Over $4 Billion

    • June 27, 2026
    Magnolia Oil & Gas Is in Lead to Acquire WildFire for Over $4 Billion

    US Natural Gas Drops on Cooler Outlooks as July Contract Expires

    • June 27, 2026
    US Natural Gas Drops on Cooler Outlooks as July Contract Expires

    US Energy Firms Add Most Rigs in a Week Since June 2022, Baker Hughes Says

    • June 26, 2026
    US Energy Firms Add Most Rigs in a Week Since June 2022, Baker Hughes Says

    Chevron Eyes More Deals to Power US Data Centers

    • June 26, 2026
    Chevron Eyes More Deals to Power US Data Centers

    US Diesel Refining Economics Remain Firm Despite Iran War Truce

    • June 26, 2026
    US Diesel Refining Economics Remain Firm Despite Iran War Truce