World’s oldest operating nuclear units back on India’s grid

Tarapur 1 and 2 are BWR units commissioned at the site in Maharashtra in 1969 as India’s first commercial nuclear power plant. Built by GE on a turnkey contract, the units were originally rated at 200 MWe but were subsequently downrated to 160 MWe (gross). They underwent six months’ refurbishment in 2005-06, and have both been offline since 2020 for major refurbishment work.

The Atomic Energy Regulatory Board announced last month that it had approved the restart and continued operation of unit 2 at the Tarapur power plant in Maharashtra on 7 May following the completion of the refurbishment undertaken by Nuclear Power Corporation of India Limited (NPCIL).

The refurbishment included the complete replacement of reactor coolant recirculation piping with forged piping and fittings made of advanced corrosion-resistant stainless steel, the regulator said, as well as safety upgrades including the commissioning of the reactor containment filtered venting system and the alternate cooling water system. During the extended outage, inspections of critical reactor components such as reactor pressure vessel welds were carried out as part of the assessment of the unit’s ageing status and residual operating life. “The evaluations have shown that the reactor can continue safe operation with the normal maintenance and surveillance programme,” the AERB said.

The regulator has given permission for the unit – known as TAPS (for Tarapur Atomic Power Station) unit 2 – to operate for a further 10 years. It issued a permit for TAPS unit 1 to restart after its refurbishment last December: that unit is now operating at its rated power of 160 MWe.

NPCIL said, in a post on social media site X, that the reconnection of both units was “a major milestone in India’s nuclear power programme … this achievement reaffirms the enduring legacy of India’s first nuclear power station and reflects the dedication, technical expertise and unwavering commitment of Team NPCIL. For over five decades, TAPS-1 & 2 have contributed to the nation’s energy security and development while providing clean, reliable and low-carbon electricity. The successful operation of both units marks another significant milestone in India’s nuclear energy journey and demonstrates the strength of indigenous capabilities, engineering excellence and a robust safety culture. As India advances towards a cleaner and more secure energy future, Tarapur continues to stand as a symbol of innovation, resilience and technological excellence”.

As well as the BWR units, the Tarapur Atomic Power Station site is home to two operating Indian-designed pressurised heavy water reactors, Tarapur 3 and 4, connected to the grid in 2005 and 2006, respectively. It has also been proposed as the site for the construction of the lead units of two Indian-designed small modular reactors: the BSMR-200, a 200 MWe reactor based on pressurised water reactor technology, and the 55 MWe SMR-55.

   

  • Related Posts

    Elementl Power plans BWRX-300 SMRs in Ohio

    Elementl has already agreed to purchase the 700-acre site 100 miles southeast of Columbus and has filed a request with PJM Interconnection to connect the site into the regional transmission…

    Concrete poured for reactor shaft at Leningrad’s eighth unit

    Over the next three months the first five tiers will be completed, up to nine metres in height. The following stages will see construction and installation work taking place simultaneously. The…

    Have You Seen?

    India Isn’t Rushing Back to Middle Eastern Oil Despite Hormuz Reopening

    • June 19, 2026
    India Isn’t Rushing Back to Middle Eastern Oil Despite Hormuz Reopening

    Philippines Seeks Long-Term Oil Supply Deal With Russia

    • June 19, 2026
    Philippines Seeks Long-Term Oil Supply Deal With Russia

    India Orders Major Strategic Oil Reserve Expansion After Supply Crisis

    • June 19, 2026
    India Orders Major Strategic Oil Reserve Expansion After Supply Crisis

    India Receives First Post-Deal LNG Cargo Through Strait Of Hormuz

    • June 19, 2026
    India Receives First Post-Deal LNG Cargo Through Strait Of Hormuz

    Beijing Steps Up Scrutiny of Indium Exports as AI Chip Demand Soars

    • June 19, 2026
    Beijing Steps Up Scrutiny of Indium Exports as AI Chip Demand Soars

    Climeworks signs 14 CO2 removal deals totalling 450,000 tonnes

    • June 19, 2026
    Climeworks signs 14 CO2 removal deals totalling 450,000 tonnes

    Oil Heads for 9% Weekly Loss as Traders Weigh US-Iran Truce Outlook

    • June 19, 2026
    Oil Heads for 9% Weekly Loss as Traders Weigh US-Iran Truce Outlook

    US Energy Firms Add Rigs for Eighth Time in Nine Weeks, says Baker Hughes

    • June 19, 2026
    US Energy Firms Add Rigs for Eighth Time in Nine Weeks, says Baker Hughes

    MAKING PROJECTS EASIER: US Eases Environmental Reviews for Natural Gas Projects

    • June 19, 2026
    MAKING PROJECTS EASIER: US Eases Environmental Reviews for Natural Gas Projects

    Biggest Ever US Clean Energy Project is Complete After Nearly Two Decades

    • June 19, 2026
    Biggest Ever US Clean Energy Project is Complete After Nearly Two Decades