HERC Cancels Connectivity For 50 MW Solar Project Due To Captive Status Dispute

Representational image. Credit: Canva

AVAADA Green HN Project Pvt. Ltd. filed a petition with the Haryana Electricity Regulatory Commission (HERC) challenging the cancellation of in-principle feasibility and final connectivity approvals for its 50 MW solar power project at the 132/33 kV Adampur substation in Hisar, Haryana. The petitioner argued that the cancellation by Haryana Vidyut Prasaran Nigam Ltd. (HVPNL) and the insistence by Dakshin Haryana Bijli Vitran Nigam Ltd. (DHBVNL) on submitting captive status documents were arbitrary and contrary to the Electricity Act, 2003, and Electricity Rules, 2005.

The petitioner had applied in 2018 for connectivity under the captive model and submitted the necessary undertaking in 2019. In-principle feasibility was granted in May 2019, and final connectivity in September 2021. However, AVAADA later sought to sell power to Haryana Discoms at a cost-plus tariff. When this proposal was rejected in 2022, the petitioner reverted to the captive model and requested the continuation of connectivity accordingly.

HVPNL canceled final connectivity in March 2024, citing non-fulfillment of conditions tied to power sale agreements. It issued a final notice in November 2024 to submit documents proving captive status. Despite further communication from AVAADA in December 2024 requesting more time, HVPNL canceled the in-principle feasibility in March 2025, stating prolonged non-compliance.

The petitioner argued that the determination of captive status is only required after commissioning, as per the Electricity Rules, and not at the connectivity stage. It also claimed that it never applied under the Haryana Solar Policy and hence should not be bound by HAREDA guidelines. However, HVPNL produced documentation showing AVAADA’s application to HAREDA under the Solar Policy, thereby negating this claim.

The Commission examined whether the connectivity procedure and Solar Policy were applicable, and whether conditions for verifying captive status at the connectivity stage violated the Act and Rules. It upheld the mandatory nature of the Commission-approved connectivity procedure and held that the Solar Policy, along with HAREDA’s guidelines, applied to the project.

Ultimately, the Commission found that AVAADA was in breach of the terms and conditions linked to connectivity, including shareholding requirements and procedural compliance under the Solar Policy. It ruled that the cancellation of both final connectivity and in-principle feasibility by HVPNL was lawful and based on valid grounds. The petition was dismissed.

 

  • Related Posts

    Philippines ERC Explores U.S. Nuclear Technology And Regulatory Cooperation For Future Energy Development

    The Energy Regulatory Commission (ERC) of the Philippines participated in the Advanced Civil Nuclear Energy Reverse Trade Mission held in the United States from October 10 to 18, 2026, to…

    Keong Hong and HELIOS Explore Solar, BESS and Data Centre Opportunities Across Four Markets

    Singapore-based building construction and property development group Keong Hong Holdings Limited has signed a Memorandum of Understanding (MOU) with Malaysia-based solar and renewable energy developer Helios Photovoltaic Sdn Bhd (HELIOS)…

    Have You Seen?

    Asian LNG Prices Surge Past $30 as Middle East Shipping Risks Escalate

    • October 20, 2026
    Asian LNG Prices Surge Past $30 as Middle East Shipping Risks Escalate

    Trump Announces $8 Billion in Emergency Diesel Relief for U.S. Farmers

    • October 20, 2026
    Trump Announces $8 Billion in Emergency Diesel Relief for U.S. Farmers

    Oil-Rich Alberta Votes to Stay in Canada in Historic Referendum

    • October 20, 2026
    Oil-Rich Alberta Votes to Stay in Canada in Historic Referendum

    LNG cargo monitoring tool launches amid shipping disruption

    • October 20, 2026
    LNG cargo monitoring tool launches amid shipping disruption

    Chemical capacity cut looms as industrial gas demand diverges

    • October 20, 2026
    Chemical capacity cut looms as industrial gas demand diverges

    Podcast | Dry ice: demand, quality and customer trust

    • October 20, 2026
    Podcast | Dry ice: demand, quality and customer trust

    Seaweed offers alternative feedstock for 420GWh UK biomethane project

    • October 20, 2026
    Seaweed offers alternative feedstock for 420GWh UK biomethane project

    Pakistan’s Growth Slows as Hormuz Crisis Hits Industry

    • October 20, 2026
    Pakistan’s Growth Slows as Hormuz Crisis Hits Industry

    Qatar Offers Lebanon 2 Gas Plants and 20 Years of LNG Piped Through Syria

    • October 20, 2026
    Qatar Offers Lebanon 2 Gas Plants and 20 Years of LNG Piped Through Syria

    Brent Tops $110 as Tanker Attacks Threaten Persian Gulf Supply

    • October 20, 2026
    Brent Tops $110 as Tanker Attacks Threaten Persian Gulf Supply