Petition For Extension And Interim Relief In 100 MW Wind-Solar Hybrid Project In Gujarat Due To Delays In Commissioning

Representational image. Credit: Canva

The petition under Section 86 (1) (c) & (f) of the Electricity Act, 2003, seeks an extension for the commissioning of the evacuation line, bays, and metering system for a 100 MW Wind Solar Hybrid Project in Gujarat. The petitioner, a renewable energy developer, had been given Stage-I connectivity in April 2023 and Stage-II connectivity in July 2023. However, delays in finalizing agreements for sharing bays with other developers have caused setbacks. The petitioner approached the Gujarat Energy Transmission Corporation (GETCO) for clarification, but due to unforeseen delays, the project may face penalties if not commissioned by January 2025.

The petitioner argues that, under the provisions of the Wind Solar Tariff Order, extensions are possible in cases of unforeseen delays. The project’s progress was stalled due to missing details from GETCO regarding the substation bays and delays in finalizing agreements with lead generators like Morjar Renewables Pvt. Ltd. The petitioner’s request to GETCO for status as a lead generator was delayed by a legal dispute between GETCO and Morjar Renewables. Meanwhile, discussions with Suzlon Global Services also failed to progress, and the project faced delays due to these issues.

During the hearing, GETCO was asked to provide crucial information related to the energization of the Kalavad 220 KV substation, including available power transformation capacity, the number of bays, and the procedures followed for sharing bays with developers. Other points raised during the hearing included the specifics of GETCO’s allocation of bays to private renewable energy developers and whether approval from the Commission is necessary for such allocation.

The respondent agreed to provide further submissions on these issues by January 22, 2025. The petitioner also filed an interlocutory application requesting interim relief, asking the Commission to prevent GETCO from taking coercive actions, such as revoking connectivity or encashing the bank guarantee, until the matter is resolved. The next hearing is scheduled for January 23, 2025. The case remains under review, with both parties expected to submit additional documents to clarify these issues.

 

  • Related Posts

    Top Stories Of The Day: Global Solar Capacity Tops 3 TW -India Ranks Second; GUVNL Launches 450 MW/900 MWh BESS Tender; GERC Proposes New Green Energy Banking Charges and More…

    Global solar power capacity surpassed the landmark 3 TW threshold after a record 664 GW of new solar installations were added during 2025. The achievement highlights the accelerating pace of…

    Week in Africa: South Africa Speeds Up RE Curtailment Claims; AfDB Approves US$100M for West Africa Renewables; Zambia Signs PPA for 500 MW Solar Project and More…

    A large solar panel array stretches across dry savanna land during sunset, illustrating renewable energy use. South Africa’s National Transmission Company South Africa (NTCSA) is accelerating the processing of renewable…

    Have You Seen?

    Tankers Emerge from Dark Mode amid Tentative Hormuz Reopening

    • June 24, 2026
    Tankers Emerge from Dark Mode amid Tentative Hormuz Reopening

    Novak: Russia Considers Complete Ban on Diesel Exports

    • June 24, 2026
    Novak: Russia Considers Complete Ban on Diesel Exports

    Europe’s Top Gas Distributor to Invest $14.8 Billion in AI-Backed Networks

    • June 24, 2026
    Europe’s Top Gas Distributor to Invest $14.8 Billion in AI-Backed Networks

    Trump Insists Iran Has Agreed to Nuclear Inspections

    • June 23, 2026
    Trump Insists Iran Has Agreed to Nuclear Inspections

    Will US and International Sanctions on Iran be Lifted?

    • June 23, 2026
    Will US and International Sanctions on Iran be Lifted?

    US Supreme Court Boosts Exxon’s Bid to Get Compensation from Cuba

    • June 23, 2026
    US Supreme Court Boosts Exxon’s Bid to Get Compensation from Cuba

    US Natural Gas Drops on Cooler Outlooks, New Pipeline Capacity

    • June 23, 2026
    US Natural Gas Drops on Cooler Outlooks, New Pipeline Capacity

    Trump Administration to Slash Oil-Drilling Bond Amount by 95%

    • June 23, 2026
    Trump Administration to Slash Oil-Drilling Bond Amount by 95%

    India Boosts U.S. LPG Imports to Record High

    • June 23, 2026
    India Boosts U.S. LPG Imports to Record High

    Iran Moves to Tap Key Asian Markets as U.S. Waives Oil Sanctions

    • June 23, 2026
    Iran Moves to Tap Key Asian Markets as U.S. Waives Oil Sanctions