Petition For Extension And Interim Relief In 100 MW Wind-Solar Hybrid Project In Gujarat Due To Delays In Commissioning

Representational image. Credit: Canva

The petition under Section 86 (1) (c) & (f) of the Electricity Act, 2003, seeks an extension for the commissioning of the evacuation line, bays, and metering system for a 100 MW Wind Solar Hybrid Project in Gujarat. The petitioner, a renewable energy developer, had been given Stage-I connectivity in April 2023 and Stage-II connectivity in July 2023. However, delays in finalizing agreements for sharing bays with other developers have caused setbacks. The petitioner approached the Gujarat Energy Transmission Corporation (GETCO) for clarification, but due to unforeseen delays, the project may face penalties if not commissioned by January 2025.

The petitioner argues that, under the provisions of the Wind Solar Tariff Order, extensions are possible in cases of unforeseen delays. The project’s progress was stalled due to missing details from GETCO regarding the substation bays and delays in finalizing agreements with lead generators like Morjar Renewables Pvt. Ltd. The petitioner’s request to GETCO for status as a lead generator was delayed by a legal dispute between GETCO and Morjar Renewables. Meanwhile, discussions with Suzlon Global Services also failed to progress, and the project faced delays due to these issues.

During the hearing, GETCO was asked to provide crucial information related to the energization of the Kalavad 220 KV substation, including available power transformation capacity, the number of bays, and the procedures followed for sharing bays with developers. Other points raised during the hearing included the specifics of GETCO’s allocation of bays to private renewable energy developers and whether approval from the Commission is necessary for such allocation.

The respondent agreed to provide further submissions on these issues by January 22, 2025. The petitioner also filed an interlocutory application requesting interim relief, asking the Commission to prevent GETCO from taking coercive actions, such as revoking connectivity or encashing the bank guarantee, until the matter is resolved. The next hearing is scheduled for January 23, 2025. The case remains under review, with both parties expected to submit additional documents to clarify these issues.

 

  • Related Posts

    Iraq Removes Customs Duties On Imported Solar Energy Systems To Boost Renewable Energy Adoption

    Iraq’s Council of Ministers has approved the removal of customs duties on imported solar energy systems to encourage the adoption of renewable energy, reduce costs for consumers, and support the…

    Solarcentury Africa Commissions 34.5 MWp Mailo 2 Solar Plant in Zambia, Raising Operational Capacity to 59.5 MWp

    Solarcentury Africa has started full commercial operations at the second phase of its Mailo solar photovoltaic (PV) plant in Zambia, adding 34.5 MWp of solar generation capacity to the country’s…

    Have You Seen?

    Ofgem Approves Deal to Keep UK Gas Import Capacity From Europe

    • October 22, 2026
    Ofgem Approves Deal to Keep UK Gas Import Capacity From Europe

    India’s Middle East Oil Imports Jumped 32% in September

    • October 22, 2026
    India’s Middle East Oil Imports Jumped 32% in September

    Grid Constraints Curtailed 119 GW of Renewables in India in September

    • October 22, 2026
    Grid Constraints Curtailed 119 GW of Renewables in India in September

    European Natural Gas Prices Rise on Middle East Escalation

    • October 22, 2026
    European Natural Gas Prices Rise on Middle East Escalation

    Delorean advances Australia biomethane project towards first gas injection

    • October 22, 2026
    Delorean advances Australia biomethane project towards first gas injection

    Iran Claims Seven Ships Hit in Persian Gulf as Oil Prices Surge

    • October 22, 2026
    Iran Claims Seven Ships Hit in Persian Gulf as Oil Prices Surge

    Record Fuel Prices Accelerate Europe’s EV Sales

    • October 22, 2026
    Record Fuel Prices Accelerate Europe’s EV Sales

    Waga Energy launches Indiana landfill RNG facility

    • October 22, 2026
    Waga Energy launches Indiana landfill RNG facility

    DAC project in Kenya targets tens of kilotonnes of CO2 for e-fuel production

    • October 22, 2026
    DAC project in Kenya targets tens of kilotonnes of CO2 for e-fuel production

    Iraq Removes Customs Duties On Imported Solar Energy Systems To Boost Renewable Energy Adoption

    • October 22, 2026
    Iraq Removes Customs Duties On Imported Solar Energy Systems To Boost Renewable Energy Adoption