Petition For Extension And Interim Relief In 100 MW Wind-Solar Hybrid Project In Gujarat Due To Delays In Commissioning

Representational image. Credit: Canva

The petition under Section 86 (1) (c) & (f) of the Electricity Act, 2003, seeks an extension for the commissioning of the evacuation line, bays, and metering system for a 100 MW Wind Solar Hybrid Project in Gujarat. The petitioner, a renewable energy developer, had been given Stage-I connectivity in April 2023 and Stage-II connectivity in July 2023. However, delays in finalizing agreements for sharing bays with other developers have caused setbacks. The petitioner approached the Gujarat Energy Transmission Corporation (GETCO) for clarification, but due to unforeseen delays, the project may face penalties if not commissioned by January 2025.

The petitioner argues that, under the provisions of the Wind Solar Tariff Order, extensions are possible in cases of unforeseen delays. The project’s progress was stalled due to missing details from GETCO regarding the substation bays and delays in finalizing agreements with lead generators like Morjar Renewables Pvt. Ltd. The petitioner’s request to GETCO for status as a lead generator was delayed by a legal dispute between GETCO and Morjar Renewables. Meanwhile, discussions with Suzlon Global Services also failed to progress, and the project faced delays due to these issues.

During the hearing, GETCO was asked to provide crucial information related to the energization of the Kalavad 220 KV substation, including available power transformation capacity, the number of bays, and the procedures followed for sharing bays with developers. Other points raised during the hearing included the specifics of GETCO’s allocation of bays to private renewable energy developers and whether approval from the Commission is necessary for such allocation.

The respondent agreed to provide further submissions on these issues by January 22, 2025. The petitioner also filed an interlocutory application requesting interim relief, asking the Commission to prevent GETCO from taking coercive actions, such as revoking connectivity or encashing the bank guarantee, until the matter is resolved. The next hearing is scheduled for January 23, 2025. The case remains under review, with both parties expected to submit additional documents to clarify these issues.

 

  • Related Posts

    AP’s Big Solar Push: 10,000 Units Per Constituency, 20 Lakh Rooftop Installations by 2025

    Representational image. Credit: Canva Andhra Pradesh Chief Minister N. Chandrababu Naidu has called for an ambitious expansion of rooftop solar power in the state, urging MLAs to facilitate the installation…

    Sungrow Italy Receives Top Brand PV 2025 Award, Strengthening its Leadership in Renewable Energy

    At the recent KEY 2025 event at Rimini Expo Center, Sungrow showcased its impressive presence alongside the announcement of a significant achievement: Sungrow Italy received the prestigious Top Brand PV…

    Have You Seen?

    AP’s Big Solar Push: 10,000 Units Per Constituency, 20 Lakh Rooftop Installations by 2025

    • March 15, 2025
    AP’s Big Solar Push: 10,000 Units Per Constituency, 20 Lakh Rooftop Installations by 2025

    Oil Rebounds 1% to End Week Steady Amid Prospect of Ukraine Ceasefire

    • March 15, 2025
    Oil Rebounds 1% to End Week Steady Amid Prospect of Ukraine Ceasefire

    Williams Says it Welcomes Trump’s Support for Constitution Gas Pipeline

    • March 14, 2025
    Williams Says it Welcomes Trump’s Support for Constitution Gas Pipeline

    Wildcatter Harold Hamm Says Shale Needs $80 Oil for Costly Fields

    • March 14, 2025
    Wildcatter Harold Hamm Says Shale Needs $80 Oil for Costly Fields

    CERAWEEK Texas LNG Aims to Make Final Investment Decision by December

    • March 14, 2025
    CERAWEEK Texas LNG Aims to Make Final Investment Decision by December

    Brazil’s Petrobras in Talks With US LNG Suppliers for Long-Term Deal, Executive Says

    • March 14, 2025
    Brazil’s Petrobras in Talks With US LNG Suppliers for Long-Term Deal, Executive Says

    Chevron Advances Plans to Develop US Data Centers With Power Generation

    • March 14, 2025
    Chevron Advances Plans to Develop US Data Centers With Power Generation

    US Oil and Gas Rig Count Unchanged This Week, Baker Hughes Says

    • March 14, 2025
    US Oil and Gas Rig Count Unchanged This Week, Baker Hughes Says

    Alaska LNG Project Could Start Up as Soon as 2030, State Governor Says

    • March 14, 2025
    Alaska LNG Project Could Start Up as Soon as 2030, State Governor Says

    ADNOC Considers Buying UAE Sovereign Fund’s Energy Assets

    • March 14, 2025
    ADNOC Considers Buying UAE Sovereign Fund’s Energy Assets